Customise Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorised as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyse the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.

No cookies to display.

BELCO Comment on Regulatory Authority Report on December 2020 Island-Wide Outage 

Bermuda Electric Light Company Limited (“BELCO”) welcomed reports published by the Bermuda Regulatory Authority (RA) on the island-wide power outage that occurred on Friday, December 18th 2020.

The incident, which occurred 18 months ago, was the result of BELCO personnel performing a standard operating procedure which led to an equipment failure at the North Power Station (NPS). This caused a cascade of built-in safety mechanisms to be triggered that ultimately shutoff power to the entire island. When the fault occurred, the safety mechanisms performed as designed and prevented what could have been serious damage to the generating equipment and grid and further delays for repairs and restoration of power.

When the incident occurred, and in the investigation that followed, BELCO was in constant communication with BWSC who built and commissioned the plant. BELCO was also in regular communication and cooperation with the RA in relation to the incident. BELCO, in collaboration with BWSC, identified the root cause of the failure and has taken steps to resolve the issue.

The BELCO investigation found that the outage resulted from a failure of the Uninterruptible Power Supply (“UPS”) that supports the NPS. Working with BWSC, the UPS was modified, tested and commissioned successfully. In addition, BELCO commissioned an independent audit performed by a third party to review of the commissioning process of the NPS which has since been providing reliable power to Bermuda for the last 18 months.

BELCO will review the reports and continue to work with the RA to implement all recommendations and actions as outlined in the reports.

 

Any content which is considered unsuitable, unlawful, or offensive, includes personal details, advertises or promotes products, services or websites, or repeats previous comments will be removed.

User comments posted on this website are solely the views and opinions of the comment writer and are not a representation of or reflection of the opinions of TNN or its staff.

TNN reserves the right to remove, edit or censor any comments.

TNN accepts no liability and will not be held accountable for the comments made by users.